Hall and Rural

Indicative Demolition Schedule for Hall and Rural

As at 30 June 2017, 1 affected house is indicatively scheduled for demolition in rural areas through to early 2018.

This is the fifth release of the Indicative Demolition Schedule, which is updated on a regular basis to reflect the changes to the demolition program.

Hall and RuralAffectedDemolished to dateMid 2017Late 2017Early 2018
HALL43010
COREE11000
JERRA10000
TENNANT11000
NICHOLLS - RURAL10000
Total85010