Indicative Demolition Schedule for South Canberra

As at 9 March 2018, 1 affected house was indicatively scheduled for demolition in South Canberra through to late 2018.

View the map of activity in South Canberra.

This is the sixth release of the Indicative Demolition Schedule, which is updated on a regular basis to reflect the changes to the demolition program.

South Canberra - NorthAffected Demolished to date Early 2018 Mid 2018 Late 2018
BARTON 1 1 0 0 0
DEAKIN 12 9 0 0 0
FORREST 5 4 0 0 1
YARRALUMLA 15 9 0 0 0
South Canberra - SouthAffected Demolished to date Early 2018 Mid 2018 Late 2018
GRIFFITH 11 11 0 0 0
NARRABUNDAH 20 15 0 0 0
RED HILL 7 7 0 0 0
Total7156001